Sonchafa · Dhanori, Pune · Greenmark Engicon Builder And Developers
Promised for 22 Aug 2018, extended once to 22 Mar 2019 — and that date has passed without the project marked complete on MahaRERA.
8 years and 3 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 22 Aug 2018 to 22 Mar 2019 (1 extension certificate on record).
- !Risk: The latest completion date on record, 22 Mar 2019, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100008475
Is Sonchafa delayed?
Yes. MahaRERA records a promised completion of 22 Aug 2018, revised to 22 Mar 2019, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100008475. The completion date moved from 22 Aug 2018 to 22 Mar 2019.
Who is the promoter?
MahaRERA records Greenmark Engicon Builder And Developers as the promoter of P52100008475.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100008475.