RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100007364

Vaastu Dreams · Chikhali, Pune · Sai Essen Vaastu Developers Llp

Promised for 12 Oct 2020 — that date has passed and MahaRERA does not mark the project complete.

6 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 12 Oct 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100007364

Is Vaastu Dreams delayed?

Yes. MahaRERA records a promised completion of 12 Oct 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100007364.

Who is the promoter?

MahaRERA records Sai Essen Vaastu Developers Llp as the promoter of P52100007364.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100007364.

Answers are generated from the record.

Data through9 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology