Skip to content

Sai Essen Vaastu Developers Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vaastu DreamsP52100007364Pimpri Chinchawad (M Corp.)2017Certificate Signed12 Oct 202012 Oct 2020On date
Vaastu Dreams IIP52100029670Chikhali2021Certificate Signed26 May 202426 May 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vaastu DreamsOn date
  • Vaastu Dreams IIOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology