Completed1 extension

P52100000080

Ace Augusta · Man, Pune · Aceaugusta

Promised for 30 Mar 2021; MahaRERA reports the project completed.

The revised date is 1 year and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2021 to 30 Sep 2022 (1 extension certificate on record).
  • Caution: 2 other MahaRERA orders name this registration.
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 17

Title report19 Jun 2017View
Building plan20 Jun 2017View
Form 120 Jun 2017View
Commencement certificate31 Oct 2017View
Registration certificate18 May 2020View
Form 17 Sep 2021View
Form 57 Sep 2021View
Extension certificate9 Sep 2021View
Show all 17 documents
Occupancy / completion certificate8 Apr 2022View
Allotment letter20 Jan 2023View
OtherView
Layout planView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 2

Questions about P52100000080

Is Ace Augusta delayed?

MahaRERA reports it completed. Its promised completion date was 30 Mar 2021.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000080. The completion date moved from 30 Mar 2021 to 30 Sep 2022.

Who is the promoter?

MahaRERA records Aceaugusta as the promoter of P52100000080.

Is it on any MahaRERA regulatory list?

2 MahaRERA orders or lists name P52100000080.

Answers are generated from the record.

Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology