Deedo IDDD-3E6AOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Ace AugustaComplaint CC005000000167632 | Not on record |
| complaint | Ace AugustaComplaint CC005000000064555 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ace AugustaP52100000080 | Man | Completed | 30 Mar 2021 | 30 Sep 2022 | +18 mo |
Aceaugusta, in questions
Does Aceaugusta finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aceaugusta registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Aceaugusta have MahaRERA regulatory cases?
2 regulatory cases name its registrations.