RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52000078189
Millennial Towers · Taloje Panchnad, Raigarh · Fsk Builders & Developers Private Limited
Promised for 12 Aug 2029, extended to 12 Dec 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 12 Aug 2029 to 12 Dec 2029.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52000078189
Is Millennial Towers delayed?
Its completion moved from 12 Aug 2029 to 12 Dec 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P52000078189. The completion date moved from 12 Aug 2029 to 12 Dec 2029.
Who is the promoter?
MahaRERA records Fsk Builders & Developers Private Limited as the promoter of P52000078189.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52000078189.