Fsk Builders & Developers Private Limited
Deedo IDDD-YFWEOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sukhkarta I Co-Operative Housing Society LimitedP51700002752 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Nilgagan Co-Operative Housing Society LimitedP51700002833 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Guru AanganP52000010422 | Ulawe | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Millennial TowersP52000078189 | Taloje Panchnad | Certificate Signed | 12 Aug 2029 | 12 Dec 2029 | +4 mo |
| The NestPR1270002502571 | Taloje Panchnad | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
| Wind CastlePR1270002601802 | Ulawe | Certificate Signed | 13 Apr 2031 | 13 Apr 2031 | On date |
Fsk Builders & Developers Private Limited, in questions
Does Fsk Builders & Developers Private Limited finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Fsk Builders & Developers Private Limited registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 3 completed on MahaRERA.
Does Fsk Builders & Developers Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.