Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52000031881

vatsalya · Koyana Velhe, Raigarh · Kalpsutra Buildcon

Promised for 31 Dec 2023 — that date has passed and MahaRERA does not mark the project complete.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate22 Nov 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000031881

Is vatsalya delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52000031881.

Who is the promoter?

MahaRERA records Kalpsutra Buildcon as the promoter of P52000031881.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000031881.

Answers are generated from the record.

Data through9 Nov 2026, 02:20SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology