Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 2 registrations with dates has moved or missed its RERA date

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
vatsalyaP52000031881Koyana VelheCertificate Signed31 Dec 202331 Dec 2023On date
AvighnaP52000032078Koyana VelheCertificate Signed31 Dec 202331 Dec 2023On date

Kalpsutra Buildcon, in questions

Does Kalpsutra Buildcon finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Kalpsutra Buildcon registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Kalpsutra Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.