RegisteredExtendedMahaRERA status: Certificate Signed

P51800051150

Shree Pinal Project · Kirol, Mumbai Suburban · Pinal Realty LLP

Promised for 21 Nov 2027, extended to 21 Mar 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 21 Nov 2027 to 21 Mar 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Jun 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800051150

Is Shree Pinal Project delayed?

Its completion moved from 21 Nov 2027 to 21 Mar 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800051150. The completion date moved from 21 Nov 2027 to 21 Mar 2028.

Who is the promoter?

MahaRERA records Pinal Realty LLP as the promoter of P51800051150.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800051150.

Answers are generated from the record.

Data through31 Oct 2026, 03:13SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology