Company or firm · first RERA registration 2023
Pinal Realty LLP
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Projects56 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
6 registrations of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Pinal ProjectP51800049614 | Kirol | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Pramukh Krupa Phase TwoP51800050490 | Mulund | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Shree Pinal ProjectP51800051150 | Kirol | Certificate Signed | 21 Nov 2027 | 21 Mar 2028 | +4 mo |
| Pramukh Krupa Phase OneP51800051702 | Mulund | Certificate Signed | 31 Mar 2025 | 31 Mar 2026 | +19 mo* |
| KevaP51800078612 | Kirol | Certificate Signed | 30 Nov 2027 | 30 Mar 2028 | +4 mo |
| Pinal EvanaPR1180002501510 | Vileparle | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology