Pinal Realty LLP

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.

Projects56 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

6 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shree Pinal ProjectP51800049614KirolCertificate Signed31 Dec 202730 Apr 2028+4 mo
Pramukh Krupa Phase TwoP51800050490MulundCertificate Signed31 Mar 202731 Jul 2027+4 mo
Shree Pinal ProjectP51800051150KirolCertificate Signed21 Nov 202721 Mar 2028+4 mo
Pramukh Krupa Phase OneP51800051702MulundCertificate Signed31 Mar 202531 Mar 2026+19 mo*
KevaP51800078612KirolCertificate Signed30 Nov 202730 Mar 2028+4 mo
Pinal EvanaPR1180002501510VileparleCertificate Signed31 Mar 202931 Jul 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology