Marathon Neopark Ashoka Wing C · Bhandup, Mumbai Suburban · Marathon Nextgen Realty Ltd
Promised for 30 Jun 2028, extended once to 30 Oct 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2028 to 30 Oct 2028 (1 extension certificate on record).
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800030752
Is Marathon Neopark Ashoka Wing C delayed?
Its completion moved from 30 Jun 2028 to 30 Oct 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800030752. The completion date moved from 30 Jun 2028 to 30 Oct 2028.
Who is the promoter?
MahaRERA records Marathon Nextgen Realty Ltd as the promoter of P51800030752.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800030752.