Marathon Nextgen Realty Ltd

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Marathon Neosquare AP51800010386Kurla2017Certificate Signed29 Dec 202331 Dec 2026+36 months
Marathon Neopark Ashoka Wing BP51800030751Kurla2021Certificate Signed31 Dec 202531 Dec 2025On date
Marathon Neopark Ashoka Wing CP51800030752Bhandup2021Certificate Signed30 Jun 202830 Oct 2028+4 months
Marathon Neopark Ashoka Wing AP51800031073Kurla2021Certificate Signed31 Dec 202531 Dec 2025On date
Mahakaleshwar Wing BP51800055887Bhandup2024Certificate Signed31 Dec 202430 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Marathon Neosquare A+36 mo
  • Marathon Neopark Ashoka Wing BOn date
  • Marathon Neopark Ashoka Wing C+4 mo
  • Marathon Neopark Ashoka Wing AOn date
  • Mahakaleshwar Wing B+12 mo

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Marathon Neosquare A (P51800010386).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology