Registered with MahaRERAP51800024024Status on MahaRERA: Lapsed

Maharashtra Mandir

Kurla, Mumbai Suburban · Promoter Adhikari Engineering Private Limited · Registered 14 Jan 2020 · Proposed completion 30 Dec 2024

Open project page
Project type
Residential / Group Housing
Revised completion
30 Dec 2025
Extension certificates
1
Last MahaRERA sync
13 Oct 2026, 01:48
On MahaRERA
Project page

What Deedo found with this number

Watch for

  • Completion date extended from 30 Dec 2024 to 30 Dec 2025 (1 extension certificate on record).
  • The latest completion date on record, 30 Dec 2025, has passed.
  • 3 other MahaRERA orders name this registration.

Documents

Stored copies of what MahaRERA published under this number.

Show all 82 documents

Regulatory orders and lists

Number not found? Deedo says “No record found in the sources Deedo currently covers” rather than guessing. It covers MahaRERA's statewide project register; new registrations appear after the next sync with MahaRERA.
Data through13 Oct 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology