Adhikari Engineering Private Limited

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
3Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Maharashtra MandirP51800024024Kurla2020Lapsed30 Dec 202430 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Maharashtra Mandir+12 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Maharashtra Mandir (P51800024024).

Regulatory cases across projects