Regulatory order: PROJECT NAME:SETHIA GRANDEUR (Regulatory Case No. 197 OF 2024) dated 30 May 2024.
30 May 2024 · matched by RERA number
View order →RERA check · free, always
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Sethia Grandeur · Andheri, Mumbai Suburban · K Maniar
Promised for 30 Dec 2020, extended once to 30 Jun 2022 — and that date has passed without the project marked complete on MahaRERA.
5 years and 11 months past the original promise today.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Regulatory order: PROJECT NAME:SETHIA GRANDEUR (Regulatory Case No. 197 OF 2024) dated 30 May 2024.
30 May 2024 · matched by RERA number
View order →Yes. MahaRERA records a promised completion of 30 Dec 2020, revised to 30 Jun 2022, which has passed, and the project is not marked complete.
Deedo holds 1 extension certificate for P51800009020. The completion date moved from 30 Dec 2020 to 30 Jun 2022.
MahaRERA records K Maniar as the promoter of P51800009020.
1 MahaRERA order or list names P51800009020.