K Maniar
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 18 mo — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sethia GrandeurRegulatory order: PROJECT NAME:SETHIA GRANDEUR (Regulatory Case No. 197 OF 2024) dated 30 May 2024. | 30 May 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sethia GrandeurP51800009020 | Andheri | Certificate Signed | 30 Dec 2020 | 30 Jun 2022 | +18 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology