RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800008566

Jyoti Chsl · Borivali, Mumbai Suburban · Ossia Developers

Promised for 30 Jun 2018, extended once to 31 Dec 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2018 to 31 Dec 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate19 Aug 2017View
Extension certificate11 Jul 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800008566

Is Jyoti Chsl delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2018, revised to 31 Dec 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800008566. The completion date moved from 30 Jun 2018 to 31 Dec 2018.

Who is the promoter?

MahaRERA records Ossia Developers as the promoter of P51800008566.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800008566.

Answers are generated from the record.

Data through4 Nov 2026, 03:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology