Ossia Developers
Company or firm · 6 projects · 6 MahaRERA registrations
Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Jyoti ChslP51800008566 | Borivali | 2017 | Not reported | 30 Jun 2018 | 31 Dec 2018 | +6 months |
| Narmada ChayaP51800032374 | Borivali | 2022 | Not reported | 15 Dec 2024 | — | On date |
| Prem RatanP51800046559 | Borivali | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Borivali Shiv Sadan CHSLP51800066573 | Kanheri | 2024 | Not reported | 15 Oct 2027 | — | On date |
| Municipal Staff Mandar ChslP51800080186 | Borivali | 2025 | Not reported | 30 Nov 2028 | — | On date |
| Tarun Yuvak Sangh ChslPR1180002600368 | Kanheri | 2026 | Not reported | 30 Sep 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 6 months, for Jyoti Chsl (P51800008566).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology