P51800007725

Lamor · Borivali, Mumbai Suburban · Sankalp Siddhi Developers Pvt Ltd

Promised for 30 Jun 2022, extended once to 29 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2022 to 29 Jun 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Jun 2023, has passed.
  • Risk: MahaRERA lists this project among projects in NCLT insolvency proceedings.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate28 Apr 2022View
OtherView

Orders 1

Listed as an NCLT insolvency project

Listed as NCLT project: LAMOR

matched by RERA number

View on MahaRERA

Questions about P51800007725

Is Lamor delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 29 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800007725. The completion date moved from 30 Jun 2022 to 29 Jun 2023.

Who is the promoter?

MahaRERA records Sankalp Siddhi Developers Pvt Ltd as the promoter of P51800007725.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51800007725.

Answers are generated from the record.

Data through9 Nov 2026, 01:52SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology