Lamor · Borivali, Mumbai Suburban · Sankalp Siddhi Developers Pvt Ltd
Promised for 30 Jun 2022, extended once to 29 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 5 months past the original promise today.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Listed as NCLT project: LAMOR
matched by RERA number
View on MahaRERAYes. MahaRERA records a promised completion of 30 Jun 2022, revised to 29 Jun 2023, which has passed, and the project is not marked complete.
Deedo holds 1 extension certificate for P51800007725. The completion date moved from 30 Jun 2022 to 29 Jun 2023.
MahaRERA records Sankalp Siddhi Developers Pvt Ltd as the promoter of P51800007725.
1 MahaRERA order or list names P51800007725.