Company or firm · first RERA registration 2017

Sankalp Siddhi Developers Pvt Ltd

Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 12 mo — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1includes insolvency
Sankalp Siddhi Developers Pvt Ltd developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 1 moved past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectLamorListed as NCLT project: LAMORNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
LamorP51800007725BorivaliCertificate Signed30 Jun 202229 Jun 2023+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology