Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800003688
The Palms · Kurla, Mumbai Suburban · Tanishq Builders
Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.
11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Deedo holds 1 extension certificate for this registration.
- !Risk: The latest completion date on record, 31 Dec 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P51800003688
Is The Palms delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800003688.
Who is the promoter?
MahaRERA records Tanishq Builders as the promoter of P51800003688.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800003688.
Answers are generated from the record.