Company or firm · first RERA registration 2017

Tanishq Builders

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 14 mo late.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay14 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mont KiaraP51900002127Mumbai CityCertificate Signed31 Mar 201930 Sep 2020+18 mo
The PalmsP51800003688KurlaCertificate Signed31 Dec 202531 Dec 2025+10 mo*
PalatinaP51800047793KurlaCertificate Signed31 Jul 202631 Jul 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology