Company or firm · first RERA registration 2017
Tanishq Builders
Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 14 mo late.
Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay14 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mont KiaraP51900002127 | Mumbai City | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| The PalmsP51800003688 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
| PalatinaP51800047793 | Kurla | Certificate Signed | 31 Jul 2026 | 31 Jul 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology