RegisteredExtendedMahaRERA status: Certificate Signed

P51700080190

Shanti Galaxy · Naupada, Thane · Shree Mahavir Urban Developers Llp

Promised for 31 Jan 2028, extended to 31 May 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2028 to 31 May 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate6 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700080190

Is Shanti Galaxy delayed?

Its completion moved from 31 Jan 2028 to 31 May 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700080190. The completion date moved from 31 Jan 2028 to 31 May 2028.

Who is the promoter?

MahaRERA records Shree Mahavir Urban Developers Llp as the promoter of P51700080190.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700080190.

Answers are generated from the record.