RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700048842

Alliaance Galaxy · Airoli, Thane · Aashutosh Enterprise

Promised for 19 Oct 2026 — that date has passed and MahaRERA does not mark the project complete.

1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 19 Oct 2026, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate24 Jan 2023View
Registration certificate16 Oct 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700048842

Is Alliaance Galaxy delayed?

Yes. MahaRERA records a promised completion of 19 Oct 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700048842.

Who is the promoter?

MahaRERA records Aashutosh Enterprise as the promoter of P51700048842.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700048842.

Answers are generated from the record.

Data through4 Nov 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology