RegisteredExtendedMahaRERA status: Certificate Signed

P51700048078

Anand 21 Uptown · Kalyan, Thane · Vpa Developers

Promised for 31 Aug 2026, extended to 31 Dec 2026, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Aug 2026 to 31 Dec 2026.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate10 Dec 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700048078

Is Anand 21 Uptown delayed?

Its completion moved from 31 Aug 2026 to 31 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700048078. The completion date moved from 31 Aug 2026 to 31 Dec 2026.

Who is the promoter?

MahaRERA records Vpa Developers as the promoter of P51700048078.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700048078.