P51700014443

Siddhi Yashwant Complex · Bhiwandi, Thane · Siddharth Narayan Tangdi

Promised for 30 Jun 2021, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

5 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate2 Dec 2017View
Extension certificate3 Jan 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700014443

Is Siddhi Yashwant Complex delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700014443. The completion date moved from 30 Jun 2021 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Siddharth Narayan Tangdi as the promoter of P51700014443.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700014443.

Answers are generated from the record.

Data through23 Nov 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology