Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700009109

Greenworld Developers Pvt. Ltd · Chikanghar, Thane · Greenworld Devlopers Pvt. Ltd

Promised for 29 Jun 2022, extended once to 29 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.

4 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 29 Jun 2022 to 29 Dec 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate19 Aug 2017View
Extension certificate8 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700009109

Is Greenworld Developers Pvt. Ltd delayed?

Yes. MahaRERA records a promised completion of 29 Jun 2022, revised to 29 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700009109. The completion date moved from 29 Jun 2022 to 29 Dec 2022.

Who is the promoter?

MahaRERA records Greenworld Devlopers Pvt. Ltd as the promoter of P51700009109.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700009109.

Answers are generated from the record.

Data through9 Nov 2026, 01:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology