Greenworld Developers Pvt. Ltd
Deedo IDDP-THN-53BNCompletion was pushed back 6 months to Dec 2022, and that date has passed too; no MahaRERA orders on record; 64% of its units are booked.
Chikanghar, Thane 421301 · Promoter: Greenworld Devlopers Pvt. Ltd.
Completion was pushed back 6 months to Dec 2022, and that date has passed too
- This projectRegistered 19 Aug 2017, completion promised 29 Jun 2022, revised to 29 Dec 2022, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700009109
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700009109 | 19 Aug 2017 | 29 Jun 2022 | 29 Dec 2022 | Greenworld Devlopers Pvt. Ltd. | Project page |
Documents50
2 documents held by Deedo, 48 filings listed on MahaRERA's project page
Finance
- PAN CardGWDPAN.pdf · uploaded 31 Jul 2017Source
Legal
- Legal Title reportTITLE CERTI(previous).pdf · uploaded 31 Jul 2017Source
- Legal Title reportTITLE1.pdf · uploaded 31 Jul 2017Source
- Legal Title reportTITLE2.pdf · uploaded 31 Jul 2017Source
- Legal Title reportTITLE3.pdf · uploaded 31 Jul 2017Source
- Declaration Form BDECLARATION PG1.pdf · uploaded 31 Jul 2017Source
Show all 50 documentsShow fewer documents
Legal
- Declaration Form BDECLARATION PG2.pdf · uploaded 31 Jul 2017Source
Migrated
- 1 PAN CardGWDPAN.pdf · uploaded 31 Jul 2017Source
- 1 Copy of the legal title reportTITLE CERTI(previous).pdf · uploaded 31 Jul 2017Source
- 2 Copy of the legal title reportTITLE1.pdf · uploaded 31 Jul 2017Source
- 3 Copy of the legal title reportTITLE2.pdf · uploaded 31 Jul 2017Source
- 4 Copy of the legal title reportTITLE3.pdf · uploaded 31 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)bldg1.pdf · uploaded 31 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)bldg2.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcc1.pdf · uploaded 31 Jul 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentcc2.pdf · uploaded 31 Jul 2017Source
- 1 Declaration in FORM BDECLARATION PG1.pdf · uploaded 31 Jul 2017Source
- 2 Declaration in FORM BDECLARATION PG2.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch1 cert.pdf · uploaded 31 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TableB (1).pdf · uploaded 31 Jul 2017Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TableB(2).pdf · uploaded 31 Jul 2017Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Rera sale area.pdf · uploaded 31 Jul 2017Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)rerA Tenant area.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RERA Form2 31-7-17.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 4)rera ARCH FORM .pdf · uploaded 31 Jul 2017Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Table-A.pdf · uploaded 1 Aug 2017Source
- 1 Details of encumbrancesEncumbrance.pdf · uploaded 2 Aug 2017Source
- 1 Building Plan Approval (IOD)cc-min.pdf · uploaded 2 Aug 2017Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 2 Aug 2017Source
- 1 Proforma of Allotment letterAuthority Letter.pdf · uploaded 2 Aug 2017Source
- 3 Commencement Certificates / NA Order for plotted developmentDoc1.pdf · uploaded 26 Oct 2017Source
- 1 Declaration about Commencement CertificateFORM D.pdf · uploaded 12 Jul 2021Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)RERA form 1.pdf · uploaded 12 Jul 2021Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 12 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM2ACROWN.pdf · uploaded 12 Jul 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM2ARESIDENCY.pdf · uploaded 12 Jul 2021Source
- 1 Disclosure of sold/ booked inventorySold and Unsold.pdf · uploaded 12 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM-5-17-18.pdf · uploaded 12 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM-5-2018-19-Signed.pdf · uploaded 12 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5-19-20-Signed.pdf · uploaded 12 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM2ACROWN.pdf · uploaded 13 Jul 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM2ARES.pdf · uploaded 13 Jul 2021Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM-5-17-18.pdf · uploaded 13 Jul 2021Source
Technical
Technical (Architect)
- DocumentRERA form 1.pdf · uploaded 12 Jul 2021Source
Technical (Engineer)
- DocumentFORM-2.pdf · uploaded 12 Jul 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals2990 PT A
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, Office 1, Office 10, Office11, Office 2, Office 3, Office4, Office5, Office6, Office7, Office8, Office9, Shop 1, Shop 2, Shop 3, Shop 4, Shop 5, Shop 6, Shop 7, 1BHK, 1 RK, 2BHK, Godown, Office space129 units in all
- Address
- 2990 Pt APIN 421301
- Village
- Chikanghar, Kalyan taluka
- Location
- 19.24116, 73.13702
- Designated bank account
- 66
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Mr Sembi Property
- South
- Bindu Tower
- East
- 12 Mtr Road
- West
- Prathamesh Darshan Chs
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking129 units
82 of 129 units booked (64%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Crown Pavillion | 2 BHK | 50.09 sq m · 539 sq ft | 1 | 1 |
| Crown Pavillion | 2 BHK | 50.53 sq m · 544 sq ft | 2 | 1 |
| Crown Pavillion | 2 BHK | 50.69 sq m · 546 sq ft | 3 | 1 |
| Crown Pavillion | 2 BHK | 53.19 sq m · 573 sq ft | 1 | 0 |
| Crown Pavillion | 2 BHK | 53.43 sq m · 575 sq ft | 8 | 4 |
| Crown Pavillion | 2 BHK | 53.66 sq m · 578 sq ft | 3 | 2 |
| Crown Pavillion | 2 BHK | 53.68 sq m · 578 sq ft | 4 | 0 |
| Crown Pavillion | 2 BHK | 54.31 sq m · 585 sq ft | 4 | 2 |
Show all 45 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Crown Pavillion | 2 BHK | 54.5 sq m · 587 sq ft | 4 | 3 |
| Crown Pavillion | 2 BHK | 54.99 sq m · 592 sq ft | 1 | 0 |
| Crown Pavillion | 2 BHK | 56.38 sq m · 607 sq ft | 1 | 0 |
| Crown Pavillion | 2 BHK | 59.87 sq m · 644 sq ft | 1 | 0 |
| Crown Pavillion | 2 BHK | 61.63 sq m · 663 sq ft | 1 | 1 |
| Crown Pavillion | Office 1 | 35.57 sq m · 383 sq ft | 1 | 0 |
| Crown Pavillion | Office 10 | 10.17 sq m · 109 sq ft | 1 | 1 |
| Crown Pavillion | Office11 | 21.39 sq m · 230 sq ft | 1 | 0 |
| Crown Pavillion | Office 2 | 32.74 sq m · 352 sq ft | 1 | 0 |
| Crown Pavillion | Office 3 | 20.76 sq m · 223 sq ft | 1 | 0 |
| Crown Pavillion | Office4 | 19.04 sq m · 205 sq ft | 1 | 0 |
| Crown Pavillion | Office5 | 35.59 sq m · 383 sq ft | 1 | 0 |
| Crown Pavillion | Office6 | 31.67 sq m · 341 sq ft | 1 | 0 |
| Crown Pavillion | Office7 | 16.57 sq m · 178 sq ft | 1 | 0 |
| Crown Pavillion | Office8 | 18.06 sq m · 194 sq ft | 1 | 0 |
| Crown Pavillion | Office9 | 11.09 sq m · 119 sq ft | 1 | 0 |
| Crown Pavillion | Shop 1 | 20.93 sq m · 225 sq ft | 1 | 0 |
| Crown Pavillion | Shop 2 | 13.34 sq m · 144 sq ft | 1 | 1 |
| Crown Pavillion | Shop 3 | 14.36 sq m · 155 sq ft | 1 | 0 |
| Crown Pavillion | Shop 4 | 19.94 sq m · 215 sq ft | 1 | 1 |
| Crown Pavillion | Shop 5 | 20.49 sq m · 221 sq ft | 1 | 0 |
| Crown Pavillion | Shop 6 | 18.81 sq m · 202 sq ft | 1 | 1 |
| Crown Pavillion | Shop 7 | 38.71 sq m · 417 sq ft | 1 | 1 |
| St Joseph Residency | 1BHK | 32.8 sq m · 353 sq ft | 2 | 2 |
| St Joseph Residency | 1BHK | 33.67 sq m · 362 sq ft | 1 | 1 |
| St Joseph Residency | 1BHK | 34 sq m · 366 sq ft | 1 | 0 |
| St Joseph Residency | 1BHK | 35.2 sq m · 379 sq ft | 1 | 0 |
| St Joseph Residency | 1BHK | 35.8 sq m · 385 sq ft | 2 | 2 |
| St Joseph Residency | 1BHK | 36.86 sq m · 397 sq ft | 4 | 4 |
| St Joseph Residency | 1BHK | 38 sq m · 409 sq ft | 1 | 1 |
| St Joseph Residency | 1 RK | 24.24 sq m · 261 sq ft | 57 | 49 |
| St Joseph Residency | 2BHK | 39.26 sq m · 423 sq ft | 1 | 0 |
| St Joseph Residency | 2BHK | 39.92 sq m · 430 sq ft | 1 | 0 |
| St Joseph Residency | 2BHK | 48.48 sq m · 522 sq ft | 3 | 0 |
| St Joseph Residency | Godown | 93 sq m · 1,001 sq ft | 1 | 1 |
| St Joseph Residency | Godown | 93 sq m · 1,001 sq ft | 1 | 1 |
| St Joseph Residency | Office space | 84.22 sq m · 907 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Varghese John | — |
| Registered real estate agent | Shopforprop Realty Private Limited | — |
Source: MahaRERA project page. Contact details are not shown.