RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700006746

Lifestyle City Kalyan Riviera · Vadavali Kh., Thane · Nirmal Lifestyle (Kalyan) Private Limited

Promised for 28 Aug 2022, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

4 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 Aug 2022 to 30 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Risk: MahaRERA lists this project among projects in NCLT insolvency proceedings.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate2 Feb 2022View
OtherView

Orders 1

Listed as an NCLT insolvency project

Listed as NCLT project: Lifestyle City Kalyan Riviera B

matched by RERA number

View on MahaRERA

Questions about P51700006746

Is Lifestyle City Kalyan Riviera delayed?

Yes. MahaRERA records a promised completion of 28 Aug 2022, revised to 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700006746. The completion date moved from 28 Aug 2022 to 30 Jun 2024.

Who is the promoter?

MahaRERA records Nirmal Lifestyle (Kalyan) Private Limited as the promoter of P51700006746.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51700006746.

Answers are generated from the record.

Data through23 Nov 2026, 01:38SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology