The Hub-B Wing · Nashik · Shree Balaji Developers
Promised for 30 Jun 2021; MahaRERA reports the project completed.
The revised date is 2 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 13 Jun 2023 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 44
Orders 0
No MahaRERA order or list names this number.
Questions about P51600018129
Is The Hub-B Wing delayed?
MahaRERA reports it completed. Its promised completion date was 30 Jun 2021.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600018129. The completion date moved from 30 Jun 2021 to 13 Jun 2023.
Who is the promoter?
MahaRERA records Shree Balaji Developers as the promoter of P51600018129.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600018129.