Shree Balaji Developers
Company or firm · 4 projects · 4 MahaRERA registrations · 1 reported completed
4Projects4 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pnt SquareP51600013917 | Nashik (M Corp.) | 2017 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| The Hub-B WingP51600018129 | Nashik | 2018 | Completed | 30 Jun 2021 | 13 Jun 2023 | +24 months |
| Shanti NiketanP51600024169 | Nashik (M Corp.) | 2020 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Shri Ram KunjP51600049058 | Nashik (M Corp.) | 2023 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for The Hub-B Wing (P51600018129).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology