P51600014676
Hari Aakruti Phase II · Nashik · Karda Constructions Limited
Promised for 30 Jun 2021, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 31 Mar 2026 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Mar 2026, has passed.
- !Caution: 1 other MahaRERA order names this registration.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 80
Title report13 Dec 2017View Encumbrance details13 Dec 2017View Commencement certificate13 Dec 2017View Registration certificate18 May 2020View Show all 80 documents
Commencement certificate15 Aug 2021View Commencement certificate1 Nov 2021View Encumbrance details9 Sep 2022View Encumbrance details23 Feb 2024View Encumbrance details23 Feb 2024View Encumbrance details23 Feb 2024View Allotment letter23 Feb 2024View Extension certificate15 Oct 2024View Questions about P51600014676
Is Hari Aakruti Phase II delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 31 Mar 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600014676. The completion date moved from 30 Jun 2021 to 31 Mar 2026.
Who is the promoter?
MahaRERA records Karda Constructions Limited as the promoter of P51600014676.
Is it on any MahaRERA regulatory list?
1 MahaRERA order or list names P51600014676.
Answers are generated from the record.
Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology