RegisteredRevised date passed1 extensionMahaRERA status: Lapsed

P51600014676

Hari Aakruti Phase II · Nashik · Karda Constructions Limited

Promised for 30 Jun 2021, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.

5 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 31 Mar 2026 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2026, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 80

Title report13 Dec 2017View
Encumbrance details13 Dec 2017View
Commencement certificate13 Dec 2017View
Form B13 Dec 2017View
Form 113 Dec 2017View
Form 529 Sep 2018View
Registration certificate18 May 2020View
Form 530 Sep 2020View
Show all 80 documents
Commencement certificate15 Aug 2021View
Form 2A25 Aug 2021View
Other7 Oct 2021View
Form 2A8 Oct 2021View
Form 2A13 Oct 2021View
Commencement certificate1 Nov 2021View
Other1 Nov 2021View
Other1 Nov 2021View
Encumbrance details9 Sep 2022View
Form 2A16 Mar 2023View
Form 2A15 Jul 2023View
Form 515 Sep 2023View
Form 515 Sep 2023View
Form 516 Sep 2023View
Form B9 Oct 2023View
Form 2A16 Oct 2023View
Form 123 Oct 2023View
Form 223 Oct 2023View
Form 2A17 Feb 2024View
Encumbrance details23 Feb 2024View
Encumbrance details23 Feb 2024View
Encumbrance details23 Feb 2024View
Allotment letter23 Feb 2024View
Other23 Feb 2024View
Form 2A29 Apr 2024View
Form B14 Aug 2024View
Form 2A8 Oct 2024View
Form 2A8 Oct 2024View
Form 28 Oct 2024View
Form 28 Oct 2024View
Other8 Oct 2024View
Other8 Oct 2024View
Form 18 Oct 2024View
Form 18 Oct 2024View
Extension certificate15 Oct 2024View
Form 223 Apr 2025View
Form 223 Apr 2025View
Form 223 Apr 2025View
Form 124 Apr 2025View
Form 124 Apr 2025View
Other24 Apr 2025View
Form 2A24 Apr 2025View
Form 2A24 Apr 2025View
OtherView
OtherView
Layout planView
Building planView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Allotment letterView
OtherView
OtherView
OtherView

Orders 1

Questions about P51600014676

Is Hari Aakruti Phase II delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 31 Mar 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51600014676. The completion date moved from 30 Jun 2021 to 31 Mar 2026.

Who is the promoter?

MahaRERA records Karda Constructions Limited as the promoter of P51600014676.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51600014676.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology