P51600004790
Kabra Heights · Nashik (M Corp.), Nashik · Manoj Madhukar Toshniwal
Promised for 31 Dec 2017; MahaRERA reports the project completed.
The revised date is 2 years and 10 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2017 to 30 Oct 2020 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 37
Orders 0
No MahaRERA order or list names this number.
Questions about P51600004790
Is Kabra Heights delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2017.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600004790. The completion date moved from 31 Dec 2017 to 30 Oct 2020.
Who is the promoter?
MahaRERA records Manoj Madhukar Toshniwal as the promoter of P51600004790.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600004790.
Answers are generated from the record.