Manoj Madhukar Toshniwal

Individual promoter · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+17 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kabra HeightsP51600004790Nashik (M Corp.)2017Completed31 Dec 201730 Oct 2020+34 months
Aastha ResidencyP51600034910Nashik2022Certificate Signed31 Dec 202531 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kabra Heights+34 mo
  • Aastha ResidencyOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 34 months, for Kabra Heights (P51600004790).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology