Completed1 extension

P51500048239

Gursahani Twin Tower · Aurangabad (M Corp.), Aurangabad · Shree Hinglajmata Constructions

Promised for 6 Oct 2024; MahaRERA reports the project completed.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 6 Oct 2024 to 5 Oct 2026 (1 extension certificate on record).
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 59

Title report4 Oct 2022View
Encumbrance details4 Oct 2022View
Encumbrance details4 Oct 2022View
Commencement certificate4 Oct 2022View
Commencement certificate4 Oct 2022View
Form 14 Oct 2022View
Form 24 Oct 2022View
Other4 Oct 2022View
Show all 59 documents
Form B6 Oct 2022View
Encumbrance details14 Oct 2022View
Allotment letter19 Nov 2022View
Other12 Dec 2022View
Other12 Dec 2022View
Registration certificate19 Dec 2022View
Form 117 Mar 2023View
Form 217 Mar 2023View
Form 122 Jul 2023View
Form 222 Jul 2023View
Other22 Jul 2023View
Form 520 Oct 2023View
Form 222 Apr 2024View
Form 523 Sep 2024View
Form 523 Sep 2024View
Form 2A7 Oct 2024View
Form 57 Oct 2024View
Extension certificate15 Oct 2024View
Other19 Jul 2025View
Other15 Oct 2025View
Form 528 Oct 2025View
Form 123 Dec 2025View
Form 223 Dec 2025View
Form 12 Feb 2026View
Form 22 Feb 2026View
Other13 Feb 2026View
Other13 Feb 2026View
Other13 Feb 2026View
Other13 Feb 2026View
Other4 Mar 2026View
OtherView
OtherView
Layout planView
OtherView
OtherView
OtherView
OtherView
OtherView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500048239

Is Gursahani Twin Tower delayed?

MahaRERA reports it completed. Its promised completion date was 6 Oct 2024.

How many extensions has it had?

Deedo holds 1 extension certificate for P51500048239. The completion date moved from 6 Oct 2024 to 5 Oct 2026.

Who is the promoter?

MahaRERA records Shree Hinglajmata Constructions as the promoter of P51500048239.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500048239.

Answers are generated from the record.

Data through3 Nov 2026, 01:58SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology