Completed

P51500030233

Sara Vatika A3 And A4 Type Building · Shendra Kamangar, Aurangabad · Sakambari Buildcon

Promised for 31 Jul 2025; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 18

Title report31 Jul 2021View
Commencement certificate31 Jul 2021View
Commencement certificate31 Jul 2021View
Form B31 Jul 2021View
Encumbrance details4 Aug 2021View
Registration certificate10 Aug 2021View
Form 514 Oct 2023View
Form 2A21 Oct 2023View
Show all 18 documents
Form 2A21 Oct 2023View
Form 522 Jan 2024View
Occupancy / completion certificate21 Nov 2024View
Occupancy / completion certificate21 Nov 2024View
Form 512 Dec 2024View
Form 417 Dec 2024View
OtherView
Layout planView
Building planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500030233

Is Sara Vatika A3 And A4 Type Building delayed?

MahaRERA reports it completed. Its promised completion date was 31 Jul 2025.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500030233.

Who is the promoter?

MahaRERA records Sakambari Buildcon as the promoter of P51500030233.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500030233.