Sakambari Buildcon
Company or firm · 4 projects · 4 MahaRERA registrations · 2 reported completed
4Projects4 RERA registrations
2Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sara VatikaP51500025439 | Shendra Kamangar | 2020 | Completed | 30 Sep 2024 | — | On date |
| Sara Vatika A3 And A4 Type BuildingP51500030233 | Shendra Kamangar | 2021 | Completed | 31 Jul 2025 | — | On date |
| Sara Vatika A2 Type BuildingP51500051540 | Shendra Kamangar | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Sara Vatika A1 BuildingP51500056311 | Shendra Kamangar | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Sara Vatika A2 Type Building (P51500051540).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology