Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Lapsed

P51500016468

Sai Shraddha Park A Building Phase 2 · Wadgaon Kolhati (Ct), Aurangabad · Vikas Laxman Chaudhary

Promised for 30 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 67

Title report26 Jul 2017View
Commencement certificate20 Apr 2018View
Encumbrance details23 Apr 2018View
Form B25 Apr 2018View
Form 111 Aug 2018View
Form 54 Nov 2018View
Form 127 Nov 2018View
Form 228 Nov 2018View
Show all 67 documents
Form 119 Feb 2019View
Form 219 Feb 2019View
Form 129 Apr 2019View
Form 230 Apr 2019View
Form 2A30 Apr 2019View
Form 2A30 Apr 2019View
Form 119 Jul 2019View
Form 219 Jul 2019View
Form 2A19 Jul 2019View
Form 18 Nov 2019View
Form 28 Nov 2019View
Form 2A8 Nov 2019View
Form 529 Nov 2019View
Form 115 Jan 2020View
Form 216 Jan 2020View
Form 2A17 Feb 2020View
Form 17 Aug 2020View
Form 27 Aug 2020View
Form 25 Dec 2020View
Form 25 Dec 2020View
Form 29 Aug 2021View
Registration certificate9 Sep 2021View
Form 114 Feb 2025View
Form 114 Feb 2025View
Form 114 Feb 2025View
Form 214 Feb 2025View
Form 214 Feb 2025View
Form 214 Feb 2025View
Form 214 Feb 2025View
Form 214 Feb 2025View
Form 2A14 Feb 2025View
Form 2A14 Feb 2025View
Other14 Feb 2025View
Other14 Feb 2025View
Other14 Feb 2025View
Other14 Feb 2025View
Other14 Feb 2025View
Form 2A27 Mar 2025View
Form 2A27 Mar 2025View
Form 2A27 Mar 2025View
Form 127 Mar 2025View
Form 117 Aug 2026View
Form 217 Aug 2026View
Other17 Aug 2026View
Form 117 Aug 2026View
Form 217 Aug 2026View
Other17 Aug 2026View
Form 2A20 Aug 2026View
OtherView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500016468

Is Sai Shraddha Park A Building Phase 2 delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500016468.

Who is the promoter?

MahaRERA records Vikas Laxman Chaudhary as the promoter of P51500016468.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500016468.

Answers are generated from the record.

Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology