Deedo IDDD-59G5Of 8 registrations whose promised date has arrived, 3 kept it (38%). The rest ran a median 16 mo late.
Delivery record
6 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Silver PearlssP51500001320 | Aurangabad (M Corp.) | Completed | 30 Nov 2018 | — | On date |
| Sai Sahyog ResidencyP51500001791 | Aurangabad (M Corp.) | Certificate Signed | 30 Nov 2019 | 28 Nov 2021 | +24 mo |
| Sai AspireP51500002358 | Aurangabad (M Corp.) | Certificate Signed | 31 Jul 2019 | 30 Jan 2021 | +18 mo |
| Sai Nakshatra Building A And B Phase- IP51500005710 | Aurangabad (M Corp.) | Completed | 31 Dec 2019 | — | On date |
| Sai Shraddha Park A Building Phase 2P51500016468 | Wadgaon Kolhati (Ct) | Lapsed | 30 Dec 2025 | — | +11 mo* |
| Sai SparshP51500016484 | Aurangabad (M Corp.) | Completed | 30 Apr 2024 | — | On date |
| Sai ApoorvaiP51500022303 | Aurangabad (M Corp.) | Lapsed | 21 Sep 2025 | — | +14 mo* |
| Sai PalaciaP51500029053 | Aurangabad (M Corp.) | Certificate Signed | 24 Apr 2024 | 24 Apr 2024 | +31 mo* |
| Sneh Manjiri ResidencyP51500033160 | Aurangabad (M Corp.) | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
| Shree Omkar ResidencyP51500033245 | Aurangabad (M Corp.) | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
Vikas Laxman Chaudhary, in questions
Does Vikas Laxman Chaudhary finish projects on time?
Of 8 MahaRERA registrations whose promised completion date has arrived, 3 kept it (38%). The rest ran a median 16 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vikas Laxman Chaudhary registered with MahaRERA?
10 projects under 10 MahaRERA registrations; 6 completed on MahaRERA.
Does Vikas Laxman Chaudhary have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.