RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50300019703
Panchratna · Amravati (M Corp.), Amravati · Ganga Builders And Developers
Promised for 30 Dec 2021; MahaRERA reports the project completed.
The revised date is 1 year and 5 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2021 to 6 May 2023 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 20
Orders 0
No MahaRERA order or list names this number.
Questions about P50300019703
Is Panchratna delayed?
MahaRERA reports it completed. Its promised completion date was 30 Dec 2021.
How many extensions has it had?
Deedo holds 1 extension certificate for P50300019703. The completion date moved from 30 Dec 2021 to 6 May 2023.
Who is the promoter?
MahaRERA records Ganga Builders And Developers as the promoter of P50300019703.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50300019703.
Answers are generated from the record.