Panchratna

Completed

Amravati (M Corp.), Amravati 444606 |Promoter: Ganga Builders And Developers

Residential / Group HousingRERAP50300019703
22 Feb 2019Registered with MahaRERA
30 Dec 2021Promised completion
6 May 2023Revised completionPushed back 1 year and 5 months
1Building
15Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
3BHK15 units in all
Land area for this project
471 sq m (5,070 sq ft)
Permissible built-up area
965 sq m (10,391 sq ft)
Sanctioned built-up area
965 sq m (10,391 sq ft)
Address
Plot No 2 Survey No 48, Village Jewad, Satyakrupa ColonyPIN 444606
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Panchratna is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 5 months

The latest completion date on record passed 3 years and 5 months ago.

Registered
22 Feb 2019
Promised
30 Dec 2021
Revised
6 May 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001970322 Feb 201930 Dec 20216 May 2023Ganga Builders And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Panchratna915

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

15 units registered

3BHK · 15 units
TypeCarpet areaUnits
3BHK56.21 sq m · 605 sq ft10
3BHK58.66 sq m · 631 sq ft5

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Panchratna

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETION CERTIFICATE RECEIVED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETION CERTIFICATE RECEIVED100%
  • Storm Water DrainsCOMPLECOMPLETION CERTIFICATE RECEIVED100%
  • Landscaping & Tree PlantingCOMPLETION CERTIFICATE RECEIVED100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETION CERTIFICATE RECEIVED100%
  • Energy managemcntCOMPLETION CERTIFICATE RECEIVED100%
  • Fire protection and fire safety requirementsCOMPLETION CERTIFICATE RECEIVED100%
  • Electrical meter room, sub-station, receiving stationCOMPLETION CERTIFICATE RECEIVED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCOMPLETION CERTIFICATE RECEIVED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

20 documents held by Deedo, 29 filings listed on MahaRERA's project page

Title

Commencement certificate

Form b

Form 2as

Registration certificate

Form 5s

Completion

Encumbrance

Extension certificate

Others

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reportSale Deed_Plot.pdf · uploaded 16 Jan 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 16 Jan 2019View
  • Building Plan Approval (IOD)Sanction Map.pdf · uploaded 16 Jan 2019View
  • OtherNotarized Partnership Deed GBD.pdf · uploaded 16 Jan 2019View
  • OtherLetter Of Authorisation.pdf · uploaded 16 Jan 2019View
  • Copy of Layout Approval (in case of layout)Layout Plan copy.pdf · uploaded 2 Feb 2019View
  • Proforma of Allotment letterDraft_Agreement to Sale.pdf · uploaded 6 Feb 2019View
  • Details of encumbrancesNon Encumbrance_Declaration.pdf · uploaded 16 Feb 2019View
  • Declaration in FORM BNotarized_FormB_GBD.pdf · uploaded 16 Feb 2019View
  • Form 2AForm2A_Mar19.pdf · uploaded 13 Jun 2019View
  • Form 2AForm2A_June19.pdf · uploaded 13 Jul 2019View
  • Annual Audit Report of Statutory CA (Form 5)GBDForm5RERA.pdf · uploaded 28 Sep 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)GBDForm5RERA.pdf · uploaded 30 Sep 2020View
  • OtherGBDForm5RERA.pdf · uploaded 30 Sep 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Signed_Form5_FY2122.pdf · uploaded 1 Jan 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)GBDForm5RERA.pdf · uploaded 1 Jan 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form5_FY2122_GBD.pdf · uploaded 2 Mar 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm4_GBD_GDB_OC_merged.pdf · uploaded 2 Mar 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameNon Encumbrance_Declaration.pdf · uploaded 6 May 2023View
  • CERSAI detailsNon Encumbrance_Declaration.pdf · uploaded 6 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)GBDForm5FY2223.pdf · uploaded 25 Apr 2024View

Promoter documents

  • Legal Title reportSale Deed_Plot.pdf · uploaded 16 Jan 2019View
  • Declaration Form BNotarized_FormB_GBD.pdf · uploaded 16 Feb 2019View

Technical documents

  • Layout ApprovalLayout Plan copy.pdfView
  • Building Plan ApprovalSanction Map.pdfView

Other legal documents

  • OtherNotarized Partnership Deed GBD.pdfView
  • OtherLetter Of Authorisation.pdfView
  • OtherGBDForm5RERA.pdfView

Proforma allotment letter

  • Proforma allotment letterDraft_Agreement to Sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

248PLOT NO 2 SURVEY NO 48

As published on MahaRERA's project page

PLOT NO 2 SURVEY NO 48

Boundaries

North
Plot No 1
South
12 M Road
East
12 M Road
West
Service Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMukesh G Sawra—
Chartered accountantAditya Oza—
Chartered accountantPankaj Pinjani—
EngineerMukesh Gurumukhdas Sawra—

Source: MahaRERA project page. Contact details are not shown.