Completed

P50100023933

Shiv Prasadam Residency · Akola (M Corp.), Akola · Satish Tulshiram Dhanokar

Promised for 21 Dec 2022; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 28

Title report28 Nov 2019View
Encumbrance details28 Nov 2019View
Commencement certificate14 Dec 2019View
Form B14 Dec 2019View
Allotment letter14 Dec 2019View
Allotment letter14 Dec 2019View
Registration certificate8 Sep 2021View
Other3 Mar 2022View
Show all 28 documents
Other3 Mar 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Allotment letter4 May 2022View
Occupancy / completion certificate23 Nov 2022View
Occupancy / completion certificate13 Jul 2023View
OtherView
Layout planView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50100023933

Is Shiv Prasadam Residency delayed?

MahaRERA reports it completed. Its promised completion date was 21 Dec 2022.

How many extensions has it had?

Deedo holds 0 extension certificates for P50100023933.

Who is the promoter?

MahaRERA records Satish Tulshiram Dhanokar as the promoter of P50100023933.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50100023933.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology