Skip to content
Deedo home
Menu

Shiv Prasadam Residency

Completed

Akola (M Corp.), Akola 444005 |Promoter: Satish Tulshiram Dhanokar

Residential / Group HousingRERAP50100023933
14 Jan 2020Registered with MahaRERA
21 Dec 2022Promised completion
1Building
10Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, 2BHK10 units in all
Land area for this project
334 sq m (3,595 sq ft)
Permissible built-up area
458 sq m (4,930 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Address
3, Congress Nagar, Khandelwal LawnPIN 444005
Designated bank account
Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Shiv Prasadam Residency is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 21 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
14 Jan 2020
Promised
21 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5010002393314 Jan 202021 Dec 2022—Satish Tulshiram DhanokarProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shiv Prasadam Residency610

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

10 units registered

1BHK · 3 units2BHK · 7 units
TypeCarpet areaUnits
1BHK52.97 sq m · 570 sq ft1
1BHK52.97 sq m · 570 sq ft1
1BHK56.21 sq m · 605 sq ft1
2BHK57.26 sq m · 616 sq ft2
2BHK59.07 sq m · 636 sq ft4
2BHK59.07 sq m · 636 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shiv Prasadam Residency

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOAR100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

28 documents held by Deedo, 35 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Allotment letters

Registration certificate

Others

Completions

Layout plans

Building plan

Document library

  • Copy of the legal title reportSearch Report Scan.pdf · uploaded 28 Nov 2019View
  • Details of encumbrancesEmcum - Satish Dhanokar-converted.pdf · uploaded 28 Nov 2019View
  • Declaration in FORM BNew FORM B 100Rs bond pdf mail.pdf · uploaded 14 Dec 2019View
  • Proforma of Allotment letterdhanokar issar pavti.pdf · uploaded 14 Dec 2019View
  • Proforma of Allotment letterdhanokar kharedi khat.pdf · uploaded 14 Dec 2019View
  • Commencement Certificates / NA Order for plotted developmentPermission Letter.PDF · uploaded 14 Dec 2019View
  • Building Plan Approval / NA Order for plotted developmentMap-converted.pdf · uploaded 14 Dec 2019View
  • Copy of Layout Approval (in case of layout)NA 1.pdf · uploaded 14 Dec 2019View
  • Copy of Layout Approval (in case of layout)NA 2.pdf · uploaded 14 Dec 2019View
  • OtherKharedi khat.pdf · uploaded 19 Dec 2019View
  • OtherLand Owner Aadhar.pdf · uploaded 19 Dec 2019View
  • Otherjpg2pdf (1).pdf · uploaded 20 Dec 2019View
  • Details of Restarting of Construction work post lockdown5th floor saction latter.pdf · uploaded 3 Mar 2022View
  • Details of Restarting of Construction work post lockdown5th floor saction plans-compressed.pdf · uploaded 3 Mar 2022View
  • Proforma of Allotment letterNew DOD1.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD2.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD3.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD4.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD5.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD6.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD7.pdf · uploaded 4 May 2022Source
  • Proforma of Allotment letterNew DOD8.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD8.pdf · uploaded 4 May 2022View
  • Proforma of Allotment letterNew DOD9.pdf · uploaded 4 May 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentshivprasadam- completion certificate.pdf · uploaded 23 Nov 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentshivprasadam- completion certificate_NEW.pdf · uploaded 13 Jul 2023View

Promoter documents

  • Legal Title reportSearch Report Scan.pdf · uploaded 28 Nov 2019View
  • Declaration Form BNew FORM B 100Rs bond pdf mail.pdf · uploaded 14 Dec 2019View

Technical documents

  • Building Plan ApprovalMap-converted.pdfView
  • Layout ApprovalNA 1.pdfView
  • Layout ApprovalNA 2.pdfView

Other legal documents

  • Otherjpg2pdf (1).pdfView
  • OtherKharedi khat.pdfView
  • OtherLand Owner Aadhar.pdfView

Proforma allotment letter

  • Proforma allotment letterNew DOD9.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Akola (M Corp.), Akola taluka

Survey, CTS, gat or plot numbers

3

As published on MahaRERA's project page

3

Boundaries

North
Plot No 2
South
Plo No 4
East
12 Fts Wise Service Line
West
30 Fts Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRagini Satish Dhanokar—
Chartered accountantPravin Baheti—
EngineerNikhli Vijaykumar Taori—
OtherRaju Parshram Dahore—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology