Construction of 30 HIG T/s. on plots of S. No. 299/1C and 299/2 at Sakegaon, Bhusawal, Dist. Jalgaon
- Project type
- Residential / Group Housing
- Revised completion
- 30 Dec 2021
- Extension certificates
- 1
- Last MahaRERA sync
- 12 Oct 2026, 01:43
- On MahaRERA
- Project page
What Deedo found with this number
- Project pageConstruction of 30 HIG T/s. on plots of S. No. 299/1C and 299/2 at Sakegaon, Bhusawal, Dist. Jalgaon
- Certificates2 PDFs · 1 extension
- Other documents16 PDFs
- Buildings on the certificate1 building
- Land parcels2 survey / CTS numbers
- Regulatory orders and listsNone
- Developer pageNashik Housing And Area Development Board
Watch for
- Completion date extended from 31 Dec 2019 to 30 Dec 2021 (1 extension certificate on record).
- The latest completion date on record, 30 Dec 2021, has passed.
Documents
Stored copies of what MahaRERA published under this number.
- Title report3 Aug 2017
- Title report3 Aug 2017
- Title report3 Aug 2017
- Encumbrance details3 Aug 2017
- Commencement certificate3 Aug 2017
- Form B3 Aug 2017
- Registration certificate31 Aug 2017
- Occupancy / completion certificate12 Jul 2021
Show all 18 documents
Number not found? Deedo says “No record found in the sources Deedo currently covers” rather than guessing. It covers MahaRERA's statewide project register; new registrations appear after the next sync with MahaRERA.
Data through12 Oct 2026, 01:43SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology