Completion was pushed back 5 months to Feb 2023, and that date has passed too; no MahaRERA orders on record; 56% of its units are booked.

Nachane (Ct), Ratnagiri 415612 · by Nisar Hassan Wagle · 0% of its projects kept the RERA date

Delivery4 yrs 2 mo latePromised Sep 2022 · revised Feb 2023 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales56% booked10 of 18 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 5 months to Feb 2023, and that date has passed too

  • This projectRegistered 7 Aug 2020, completion promised 30 Sep 2022, revised to 28 Feb 2023, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52800026002
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P528000260027 Aug 202030 Sep 202228 Feb 2023Nisar Hassan WagleProject page
Documents31

3 documents held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN Cardpan card.pdf · uploaded 9 Jul 2020Source

Legal

  • Legal Title reportSearch.pdf · uploaded 9 Jul 2020Source
  • Declaration Form BForm B.pdf · uploaded 28 Jul 2020Source

Migrated

  • 1 PAN Cardpan card.pdf · uploaded 9 Jul 2020Source
  • 1 Copy of the legal title reportSearch.pdf · uploaded 9 Jul 2020Source
Show all 31 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 9 Jul 2020Source
  • 1 Copy of Layout Approval (in case of layout)wagle plan.pdf · uploaded 9 Jul 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentCollector.pdf · uploaded 9 Jul 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentwagle permission.pdf · uploaded 9 Jul 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentPrant.pdf · uploaded 9 Jul 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 9 Jul 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 9 Jul 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 9 Jul 2020Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 28 Jul 2020Source
  • 1 Proforma of Allotment letterAgrement to sale draft.pdf · uploaded 28 Jul 2020Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 28 Jul 2020Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 27 Sep 2022Source
  • 1 Declaration about Commencement CertificateDeclaraion.pdf · uploaded 22 Oct 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 22 Oct 2022Source
  • 2 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 22 Oct 2022View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 22 Oct 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 22.pdf · uploaded 19 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 21.pdf · uploaded 19 Nov 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 22.pdf · uploaded 19 Nov 2022Source

Technical

  • Documentwagle plan.pdf · uploaded 9 Jul 2020Source
  • DocumentCollector.pdf · uploaded 9 Jul 2020Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 9 Jul 2020Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 9 Jul 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S No 381 H No 1/4/A/36 CTS No 621/36

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Basement, Shop18 units in all
Address
S No 381 H No 1/4/A/36 CTS No 621/36, Nachane, NachanePIN 415612
Village
Nachane (CT), Ratnagiri taluka
Land area for this project
480 sq m (5,167 sq ft)
Permissible built-up area
673 sq m (7,241 sq ft)
Sanctioned built-up area
618 sq m (6,649 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

S No 381 H No 1/4/A/36 CTS No 621/36

Land as published on MahaRERA's project page

S No 381 H No 1/4/A/36 CTS No 621/36

Boundaries

North
Property owned by Mr Manjarekar
South
Service Road
East
Property owned by Mr Marathe
West
Property owned by Mr Pangarkar

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

10 of 18 units booked (56%), as the promoter reported to MahaRERA

1BHK · 7 units2BHK · 6 unitsBasement · 1 unitShop · 4 units
TypeCarpet areaUnitsBooked
1BHK33.78 sq m · 364 sq ft31
1BHK33.92 sq m · 365 sq ft30
1BHK38.33 sq m · 413 sq ft11
2BHK43.15 sq m · 464 sq ft33
2BHK43.84 sq m · 472 sq ft31
Basement78.92 sq m · 849 sq ft10
Shop14.16 sq m · 152 sq ft11
Shop15.96 sq m · 172 sq ft11
Shop17.18 sq m · 185 sq ft11
Shop19.51 sq m · 210 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNilesh M Gundecha—
Chartered accountantUmesh Lovalekar & Co—
EngineerSandeep S Shetye—
OtherSufiyan Siraj Pathan—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Nachane (Ct)

All 121 projects in Nachane (Ct) · Compare Radhakrishna Enclave with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology