RERA projects in Nachane (Ct)
120 projects under 122 MahaRERA registrations, registered 2017–2026. 6% have a completion date extended beyond the one promised.
120RERA projects
122Registrationssome projects hold several
48Completion still due74 past their completion date
26 monthsMedian extension beyond promised date6% of registrations extended
1Regulatory caseson 1 project
15Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 28 |
| 2018 | 14 |
| 2019 | 11 |
| 2020 | 10 |
| 2021 | 11 |
| 2022 | 11 |
| 2023 | 9 |
| 2024 | 9 |
| 2025 | 11 |
| 2026 | 8 |
Projects in Nachane (Ct)
120 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aashirwad ComplexSaukhyam Constructions | P52800009508 | 22 Aug 2017 | 28 Feb 2018 | — | Promised date passed | 0 |
| Amey ResidencyManoj Sham Ghude | P52800009400 | 22 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Shree Swami Samarth HeightsAvani Realtors & Developers | P52800009106 | 19 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Anmol HillsideAnmol Builders & developers | P52800008337 | 18 Aug 2017 | 30 Sep 2020 | 30 Nov 2022 | Extended 26 mo | 0 |
| Sea BreezeSandeep Shashikant Nerlekar | P52800008367 | 18 Aug 2017 | 15 Aug 2018 | — | Promised date passed | 0 |
| Oracle ResidencyNuruddin Abdulrehman Tandel | P52800007479 | 17 Aug 2017 | 26 Jan 2019 | — | Promised date passed | 0 |
| Aadinath TaranganArihant Vastu Nirman Pvt. Ltd | P52800004447 | 9 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Kohinoor PrestigeJain And Jain Construction Company | P52800004038 | 7 Aug 2017 | 30 Nov 2020 | — | Promised date passed | 0 |
| Shri Swami Samarth LeelaShree Swami Samarth Developers | P52800003703 | 6 Aug 2017 | 31 May 2018 | 30 Sep 2018 | Extended 4 mo | 0 |
| Laxmi ParadiseAshtagandha Construtions | P52800003415 | 5 Aug 2017 | 15 Nov 2023 | — | Promised date passed | 0 |
| Shivleela SankulSoham Promoters And Builders | P52800003430 | 5 Aug 2017 | 10 Aug 2019 | — | Promised date passed | 0 |
| Hilltop EstatesUnity Associates | P52800003033 | 4 Aug 2017 | 1 Dec 2018 | — | Promised date passed | 0 |
| Ksp ComplexSujata Krishnat Powar | P52800002005 | 31 Jul 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Arijeet ResidencyRahul Builders And Developers | P52800001942 | 29 Jul 2017 | 18 Oct 2018 | — | Promised date passed | 0 |
| omkar residencyM/s Pavan and JM Construction co | P52800001744 | 29 Jul 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Shri Mahalaxmi SankulShri Mahalaxmi Builders & Developers | P52800001055 | 25 Jul 2017 | 30 Sep 2020 | — | Promised date passed | 0 |
| Shree Samarth PrakashShree Swami Developers | P52800000535 | 18 Jul 2017 | 31 Mar 2018 | 30 Jun 2022 | Extended 51 mo | 1 |
| Tanushree PlazaSameer Ramesh Sawant | P52800000185 | 10 Jul 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Aadinath NagarArihant Vastu Nirman Pvt. Ltd | P52800000156, P52800020423 | 5 Jul 2017 | 30 Dec 2026 | — | Not yet due | 0 |
| Arihant PlatinoArihant Vastu Nirman Pvt. Ltd | P52800000027 | 13 Jun 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
Other localities in Ratnagiri
- Zadgaon Ct51 projects
- Ratnagiri (M Cl)34 projects
- Rahataghar20 projects
- Khedshi18 projects
- Kuwarbav (Ct)14 projects
- Padavewadi9 projects
- Karvanchiwadi8 projects
- Ganapatipule3 projects
- Malgund3 projects
- Mirjole3 projects
- Tiwandewadi3 projects
- Bhagaavatinagar2 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Arihant Vastu Nirman Pvt. Ltd5 projects
- Prasad Prabhakar Waghdhare5 projects
- Akar Infrastructure3 projects
- Gowardhan Builders & Developers3 projects
- Sameer Ramesh Sawant3 projects
- Samruddhi Developers3 projects
- Soham Promoters And Builders3 projects
- Avani Realtors & Developers2 projects
- Jain And Jain Construction Company2 projects
- Mahesh Suresh Gundecha2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology