Promised date passed6 floorsRERA P52000020780
Main building, MP Pride
Deedo IDDP-RAI-ST1T-MPMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked93%13 of 14 · MahaRERA
Completion30 Dec 2022as registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 27.4 m² (294 sq.ft) | 3 | 3 |
| 1RK | 17.1 m² (184 sq.ft) | 1 | 1 |
| 1RK | 17.1 m² (184 sq.ft) | 3 | 3 |
| 1RK | 17.8 m² (191 sq.ft) | 4 | 3 |
| 1RK | 19.5 m² (210 sq.ft) | 1 | 1 |
| SHOPS | 4.3 m² (47 sq.ft) | 1 | 1 |
| SHOPS | 6.2 m² (67 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P52000020780 · registered 9 May 2019
- Promised completion
- 30 Dec 2022
- Revised completion
- 30 Dec 2022
- Sanctioned habitable floors
- 6
- Building
- MP Pride
- Sanctioned floors (incl. basement, stilt, podium)
- 6
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-RAI-ST1T-MP
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 30 Dec 2022.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through12 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology