JW Pride
Deedo IDDP-RAI-BH0XCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 39% of its units are booked.
Vadghar (Ct), Raigarh 410206 · by Jw Infra
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 15 Feb 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000054879
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000054879 | 15 Feb 2024 | 31 Dec 2027 | 30 Apr 2028 | JW Infra | Project page |
Documents66
1 document held by Deedo, 65 filings listed on MahaRERA's project page
Finance
- PAN CardJW Infra Pancard.pdf · uploaded 20 Jan 2024Source
Legal
Show all 66 documentsShow fewer documents
Migrated
- 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 20 Jan 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance -Legal.pdf · uploaded 20 Jan 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 20 Jan 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance -Legal.pdf · uploaded 20 Jan 2024Source
- 1 Copy of Layout Approval (in case of layout)Plan jw-1.pdf · uploaded 20 Jan 2024Source
- 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development (3).pdf · uploaded 20 Jan 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 20 Jan 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 20 Jan 2024Source
- 1 Declaration in FORM BNotarised Form B -JW Pride.pdf · uploaded 20 Jan 2024Source
- 1 CERSAI detailsCersai Declaration.pdf · uploaded 20 Jan 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)output (2).pdf · uploaded 20 Jan 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnnexure A -Merged.pdf · uploaded 20 Jan 2024Source
- 1 Proforma of Agreement for saleAFS_Short Title_JW Pride_JW Infra_20012024.pdf · uploaded 20 Jan 2024Source
- 1 Proforma of Allotment letterAllotment Letter_Short title_JW Pride_JW Infra_20012024.pdf · uploaded 20 Jan 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 20 Jan 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation -Allotment.pdf · uploaded 20 Jan 2024Source
- 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement (24).pdf · uploaded 20 Jan 2024Source
- 1 Other – TechnicalAnnexure A-Undertaking - Copy.pdf · uploaded 20 Jan 2024Source
- 1 Other – LegalLEASE JW (1).pdf · uploaded 22 Jan 2024Source
- 2 Other – LegalAnnexure A-Undertaking - Copy.pdf · uploaded 22 Jan 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - JW Pride 31-03-2024.pdf · uploaded 28 Mar 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - JW Pride 30-06-2024.pdf · uploaded 28 Mar 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - JW Pride 30-09-2024.pdf · uploaded 28 Mar 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - JW Pride as on December 2024.pdf · uploaded 28 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - JW Pride as on March 2024.pdf · uploaded 28 Mar 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - JW Pride as on June 2024.pdf · uploaded 28 Mar 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - JW Pride as on September 2024.pdf · uploaded 28 Mar 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - JW Pride as on December 2024.pdf · uploaded 28 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 JW Pride FY 2023-24.pdf · uploaded 28 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)JW Pride - Form 1 March 2024.pdf · uploaded 9 May 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)JW Pride - Form 1 June 2024.pdf · uploaded 9 May 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)JW Pride - Form 1 September 2024.pdf · uploaded 9 May 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)JW Pride - Form 1 December 2024.pdf · uploaded 9 May 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)JW Pride - Form 1 March 2025.pdf · uploaded 9 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)JW Pride - Form 3 March 2024.pdf · uploaded 9 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)JW Pride - Form 3 June 2024.pdf · uploaded 9 May 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)JW Pride - Form 3 September 2024.pdf · uploaded 9 May 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)JW Pride - Form 3 December 2024.pdf · uploaded 9 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)JW Pride - Form 2 March 2024.pdf · uploaded 9 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)JW Pride - Form 2 June 2024.pdf · uploaded 9 May 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)JW Pride - Form 2 September 2024.pdf · uploaded 9 May 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)JW Pride - Form 2 December 2024.pdf · uploaded 9 May 2025Source
Technical
Technical (Architect)
- DocumentJW Pride - Form 1 March 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 1 June 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 1 September 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 1 December 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 1 March 2025.pdf · uploaded 9 May 2025Source
Technical (Engineer)
- DocumentForm 2 - JW Pride as on March 2024.pdf · uploaded 28 Mar 2025Source
- DocumentForm 2 - JW Pride as on June 2024.pdf · uploaded 28 Mar 2025Source
- DocumentForm 2 - JW Pride as on September 2024.pdf · uploaded 28 Mar 2025Source
- DocumentForm 2 - JW Pride as on December 2024.pdf · uploaded 28 Mar 2025Source
- DocumentJW Pride - Form 2 March 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 2 June 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 2 September 2024.pdf · uploaded 9 May 2025Source
- DocumentJW Pride - Form 2 December 2024.pdf · uploaded 9 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No 199, Sector R3
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Landowner 1BHK, Landowner Shop, Shop31 units in all
- Address
- Plot No - 199, Sector - R3, Sector -R3, Vadghar - Pushpak NodePIN 410206
- Village
- Vadghar (CT), Panvel taluka
- Location
- 18.98382, 73.10355
- Land area for this project
- 400 sq m (4,304 sq ft)
- Permissible built-up area
- 1,400 sq m (15,069 sq ft)
- Sanctioned built-up area
- 507 sq m (5,457 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No - 199 , Sector - R3
Boundaries
- North
- 11 Mtr Wide Road
- South
- Plot No -208- 209 -210
- East
- Plot No -200
- West
- Plot No -198
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking31 units
12 of 31 units booked (39%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 26.68 sq m · 287 sq ft | 2 | 1 |
| 1BHK | 26.76 sq m · 288 sq ft | 4 | 1 |
| 1BHK | 27.77 sq m · 299 sq ft | 8 | 6 |
| 1BHK | 29.49 sq m · 317 sq ft | 8 | 4 |
| 1BHK | 29.9 sq m · 322 sq ft | 1 | 0 |
| Landowner 1BHK | 28.25 sq m · 304 sq ft | 2 | 0 |
| Landowner 1BHK | 28.99 sq m · 312 sq ft | 2 | 0 |
| Landowner 1BHK | 29.9 sq m · 322 sq ft | 1 | 0 |
| Landowner Shop | 23.43 sq m · 252 sq ft | 2 | 0 |
| Shop | 23.43 sq m · 252 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.