57 projects under 57 MahaRERA registrations, registered 2017–2025. 47% have a completion date extended beyond the one promised.

Locality
57RERA projects
57Registrations
16Completion still due41 past their completion date
12 monthsMedian extension beyond promised date47% of registrations extended
0Regulatory casesnone on MahaRERA's lists
67Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201718
20187
20199
20202
20213
20222
20235
20245
20256

Projects in Uran

57 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
AstrovaKalpana Sterling Infra LLPP5200002234016 Sep 201931 Jul 202631 Jul 2026Promised date passed0
Tulsi ViharPawan DevelopersP5200002127518 Jun 201930 May 202230 May 2022Promised date passed0
Advance HarmonyRamesh Dungarshi ShahP5200002084015 May 201930 Dec 202230 Dec 2022Promised date passed0
Hari SakhaNiyati Homes LLPP520000207458 May 201926 Dec 202426 Dec 2024Promised date passed0
Tulsi AanganOm Buildcon Infrastructures Private LimitedP5200002045311 Apr 201930 Mar 202330 Mar 2023Promised date passed0
Sai DarshanSai Krupa DevelopersP5200001930623 Jan 201930 Mar 202330 Mar 2023Promised date passed0
Uma GreensMurudeshwar DevelopersP5200001928215 Jan 201930 Sep 202630 Sep 2026Promised date passed0
Nazir Shet ApartmentsZiaulmajid Nazir SondeP5200001848712 Nov 201830 Dec 202230 Dec 2022Promised date passed0
Vaishnavi EmperiaRk Group Of InfraP520000180203 Oct 201829 Nov 202729 Nov 2027Not yet due0
AvhniAaum ConstructionsP520000166725 Jun 201830 Sep 202030 Mar 2022Extended 18 mo0
Sai GauravSai Shakti BuilderP5170001650218 May 201830 Jun 202231 Mar 2026Extended 45 mo0
Daji ResidencyVw RealtyP520000155608 Mar 201830 Dec 202330 Dec 2023Promised date passed0
Globe ApartmentV. Kumar InfratechP5200001532615 Feb 201828 Feb 202228 Feb 2022Promised date passed0
Sai TaraShree Hari GroupP5200001490111 Jan 201830 Mar 202231 Mar 2026Extended 48 mo0
Sana ResidencyMohd Faizal Mohd Yasin MansuriP5200001464020 Dec 201731 Dec 201831 Dec 2018Promised date passed0
R N HeightsRavechi Builder India Private LimitedP5200001418413 Nov 201731 Dec 202631 Dec 2026Not yet due0
Arham ViewGalaxy EnterpriseP5200001378425 Oct 201730 Mar 202230 Mar 2023Extended 12 mo0
Sarah CastleHomecraft Builders And DevelopersP520000126316 Sep 201730 Jun 201930 Dec 2020Extended 18 mo0
Pawan ResidencyPawan EnterpriseP5200001179931 Aug 201731 May 201931 May 2019Promised date passed0
Shalom RegencyJacob GeorgeP5200001010124 Aug 201730 Sep 201930 Jun 2023Extended 45 mo0
SerenaMaverick Developers DronagiriP5200000948122 Aug 201730 Dec 202131 Dec 2022Extended 12 mo0
Shalom ArcadeJacob GeorgeP5200000920922 Aug 201731 Mar 202030 Mar 2022Extended 24 mo0
VaishnaviPramod Vasant BhoirP5200000878719 Aug 201731 Aug 201831 Aug 2018Promised date passed0
Ramesh RegencyTansukh Pannalal JainP5200000624514 Aug 201730 Jun 201830 Jun 2018Promised date passed0
Erasali DivineA A Thaiup Ali Abdul MadinaP5200000538011 Aug 201731 Dec 201831 Dec 2018Promised date passed0

Other localities in Uran

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Cielo Heights2 projects
  2. Devkrupa Enterprises2 projects
  3. Jacob George2 projects
  4. Murudeshwar Developers2 projects
  5. A A Thaiup Ali Abdul Madina1 project
  6. Aaum Constructions1 project
  7. Abm Omcon Land Developers1 project
  8. Apex Realty1 project
  9. Baldev Diwan Singh1 project
  10. Furqan Shafi Navrange1 project
Data through14 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology